Tottenham Hotspurs Football Ground

  • London
  • Commercial
  • Programming
Trade contractors on Tottenham Hotspurs new Football Ground have appointed us as their live planning support for the duration of the works. The scheme comprises of 2 stages; Stage 1 – Establish the baseline programme associated with the trade contractor’s packages of works covering mechanical and electrical systems. Stage 2 –Undertake monthly updates to the baseline programme in order to support the trade contractor’s progress of works to satisfy the contractual requirements under its contract with Tottenham Hotspurs Football Club. We continue to be supporting this project until contract completion.